We employed the same tunnelling methods as T5 for the Heathrow
Express and Piccadilly Line extension tunnels. Historic-al factors
meant that there were differences in the ways each job started and
finished, however.
When the Heathrow Express was built the construction of T5 was
already on the horizon and stub tunnels were constructed, enabling
tunnel boring machines to drive straight off with-out disrupting
services to Heathrow Terminals 1, 2, 3 and 4.
To construct the new twin Piccadilly Line bores, Morgan Vinci first
had to excavate a box from which to launch its tunnel boring
machines (TBMs). Meanwhile, to connect the new tunnels with the
existing Piccadilly Line at Terminals 1, 2 and 3 our team had to
construct a new junction box. This has a larger cross-section than
the adjoining tunnels, extending close to water-bearing gravels
overlying the London clay through which the tunnels themselves were
driven. We selected top down construction over the alternative of
driving bored tunnels all the way and then enlarging them to make
space for the connection.
Top down construction involves installing contiguous piled walls
and then casting a reinforced concrete slab on the ground. Once the
concrete has cured and gained strength, ground beneath the slab is
excavated – the slab becomes a roof. Once final depth has been
reached a base slab is cast. The technique was selected to
eliminate the risk of hitting the water-bearing gravels and enabled
Morgan Vinci to use an open-face TBM rather than a more expensive
earth pressure balance machine, which would have been essential to
deal with ground water.
Bachy Soletanche installed diaphragm walls for the junction box
through the existing Piccadilly Line tunnels at the start of a 20
month line closure and possession, allowing the box to be
excavated. The bored tunnels stopped just shy of the box – the TBMs
retreated the way they had come so that the drives would not risk
destabilising the existing tunnels. We created short lengths of
hand dug, sprayed concrete-lined tunnel to make the connection.
Both lines terminate in a shared cut and cover station box,
nestling under the main Terminal 5 building. This is equipped with
six platforms in all, in anticipation of high-speed rail links from
west of Heathrow and/or the arrival of Crossrail.