
The 1.2km, twin bore airside road tunnels (ART) are, at 8.8m
diameter, the largest of the five new T5 tunnels and required
particularly delicate tunnelling. The ART crosses the existing
Piccadilly Line tunnel with 3m clearance and the Heathrow Express
tunnel with 5m clearance. Excessive movement of either existing
tunnel would endanger rail-way operation and could force suspension
of services.
The airside road tunnel also passes beneath taxiways. Ground
movement resulting from tunnelling had to be limited to ensure the
safety of BAA’s operations. This was achieved in a number of
ways.
We tuned the vertical and horizontal alignment of the ART to
minimise the influence of tunnelling. In plan, the tunnel is curved
to avoid as far as possible taxiways and apron areas, while in
elevation it undulates, with a
W-shaped profile.
Near the portals at either end the twin bores of the ART are
extremely shallow. Risk assessments showed that if excavation broke
out of the stable London clay stratum into the overlying gravel
layer, there was a danger that settlement could result. Therefore,
before tunnel driving
started, we excavated the gravel within 2m of the tunnel crown
adjacent to the location of the portals and replaced it with
concrete.
From the portals the tunnel bores descend and run for a length at
depth, well within London clay which, though subject to swelling,
is a stable material meaning that risk of ground movement is
reduced. The airside road tunnel rises to clear the Piccadilly Line
and Heathrow Express tunnels, but drops in between them to maintain
maximum depth.
To minimise ground movement we designed a bespoke tunnel boring
machine (TBM), allowing pressure to be maintained on the tunnel
face even while the ground was being gouged away. Earth pressure
balance TBMs are well established for soft and variable ground but
had never previously been used in London clay, which is stable and
generally considered an ideal material for tunnelling.
The decision to go for an earth pressure balance machine was taken
because risk assessments identified the potential for settlement,
over the shallower sections of the drive, of as much as 150mm using
a conventional TBM.
German TBM supplier Herrenknecht designed a machine that would
maintain pressure equal to that of the surrounding ground through
use of compressed air. This prevented ground collapsing ahead of
the TBM as it advanced, so keeping ground settlement within
tolerable limits. Grout was injected into the gap left between the
ground and the tunnel lining as the TBM advanced in order to
prevent relaxation of the ground causing settlement.
Settlement was closely monitored during excavation through the use
of instrumentation within the rail tunnels and on the surface, and
surveys
for distortion.
Airside road tunnel portals
At the airside road tunnel portals the transition from tunnel to
ground level
is made in cut and cover boxes – we constructed piled walls,
excavated the ground between the walls and constructed the base and
roof slabs. Conventionally the piled walls would have been propped
with massive temporary steel struts to resist overturning forces
imposed by the surrounding ground as excavation advanced. But
careful analysis of the piles combined with a carefully planned
construction methodology enabled us to eliminate the struts, saving
31 weeks on the excavation programme and greatly reducing the
safety risk associated with handling and erecting temporary steel
struts.
The piled walls were deemed to be strong enough to work in
cantilever mode during excavation, but were closely monitored as
excavation advanced. We carefully orchestrated the excavation
sequence itself, removing soil in 500mm bands and monitoring levels
using laser surveying equipment.
We provided temporary support at intermediate levels as work
advanced by pouring concrete slabs directly onto the base of the
excavation – the slabs acted as struts, bracing the piled walls.
They were progressively broken out as excavation to full depth
advanced and the permanent base slab was cast.
Meanwhile, if movement was detected, additional slabs could quickly
be installed by our team to provide support and prevent excessive
deformation. We designed for the job a special concrete mix that
cured and provided strength quickly.
In fact, no unplanned propping was needed.