
There are five new tunnels serving Terminal 5 with a combined
length of approximately 14km. Tunnelling accounted for some £650
million of the total £4.3 billion
T5 construction budget.
Twin bore tunnels for London Underground’s Piccadilly Line and the
Heathrow Express rail link were extended by 1.7km and 1.6km
respectively. A 1.3km long road tunnel was built to provide airside
vehicle access to T5 from the rest of the Heathrow complex,
crossing above both Piccadilly Line and Heathrow Express tunnels
and beneath taxiways. A 4.1km, 3m diameter stormwater outfall
tunnel provides drainage for the extensive areas of new
hardstanding and taxiway. And there are new passenger track transit
and baggage transfer tunnels linking all three T5 buildings.
Ground movements arising from tunnelling were considered one of the
major risks because of their potential to damage existing
infrastructure and cause disruption to rail services or airport
operations.
Monitoring and control of ground movement was accordingly a key
part of the risk management strategy. While the majority of
tunnelling has been carried out using tunnel boring machines
(TBMs), innovative developments of a single shell shotcrete lined
tunnelling method, called Lasershell, were used for construction of
the numerous short, complex, tunnels associated with the main
bores.
Risks associated with tunnelling have been reduced by handing
construction for all of the tunnels to the same firms. Mott
MacDonald carried out design of all tunnels and construction
supervision. We also provided specialist advice and interpretation
of data from settlement monitors.
A joint venture of Morgan Est and Vinci Grand Projects was
tunnelling contractor; Balfour Beatty Rail Projects installed rail
and traction power in the two rail tunnel extensions; and Balfour
Kilpatrick carried out mechanical and electrical fit-out.
Tunnelling techniques
We carried out construction of the airside road tunnel, Piccadilly
Line and Heathrow Express rail extensions and the stormwater
outfall tunnel using tunnel boring machines (TBM). Linings for all
four consist of precast concrete segments. Those making up the rail
and stormwater outfall tunnels use a wedgeblock system, in which
lining segments are held in place by the compressive force exerted
by the surrounding ground. Lining for the airside road tunnel
consists of bolted segments with rubber gaskets waterproofing the
joints. This is because sections of the airside road tunnel are at
the interface between impermeable London clay and water-bearing
terrace gravels lying above.
We constructed the tracked transit tunnel, connecting the
concourses of the main T5 terminal building and its two satellites,
using the cut-and-cover method.