
Our design and cost model showed that by increasing the
strength of the PQC we could significantly reduce the pavement
depth. An increase in the flexural strength from 6N/mm2
– the standard pavement mix – to 7N/mm2 would result in
an average reduction of 80mm.
Applying this reduction to the 1 million square metres of Terminal
5 aircraft pavements would result in substantial cost, programme
and environmental benefits. Reducing the pavement depth also
resulted in less clay having to be transported from the main
site.
To achieve a 7N/mm2 strength concrete the design and
construction teams commenced mix development in 1999. Increased
strength was obtained by reducing the water/cement ratio, resulting
in a very dry concrete mix. Tight control of raw materials –
aggregate moisture content and grading, and cement and PFA chemical
properties – was critical to achieving consistent strength. The
Terminal 5 concrete mix had a total cementitious content of
380kg/m3 with 30% pulverised fly ash, and contained
limestone aggregate.
All members of the supply chain were involved from an early stage
to ensure that a workable high strength mix could be achieved. A
large number of laboratory and full scale production trials were
carried out and the concrete was tested on a number of other BAA
airfield projects at Heathrow, Gatwick and Stansted prior to use at
Terminal 5.
Trials showed that to achieve success the concrete batching and
paving processes had to be integrated into a single system. A
dedicated PQC batching plant was established on site.
Thrifty design
Another innovation was the use of recycled concrete in the
pavement’s cement bound base layer. Combined with reducing slab
thickness through the use of high strength concrete, it is reckoned
that 27,000 truck movements were eliminated.
To further minimise the volume of PQC required, the pavement was
designed for the specific traffic forecast in each area. For
example, areas adjacent to the terminal buildings were designed for
aircraft tugs only and detailed forecasts were used to design each
taxiway and groups of aircraft stands. Central sections of the
stands, subject to higher loading, were of deeper construction than
the edges. This innovation reduced the PQC volume by
1,400m3.