
When detailed design got under way in late 2001 the desire was
to construct piles as open bores without any support to the pile
walls prior to concreting, as this would be the most economic and
programme efficient option. But the length of piles was limited by
the local geology. At a depth of around 50m the London clay becomes
granular and water-bearing. Water entering the bottom of a pile
bore would make it susceptible to collapse. Open bore piles would
therefore have to terminate above this level.
Prevented from installing long piles by ground conditions, it
became necessary for us to utilise a combination of
straight-shafted and underreamed piles (piles with an enlarged
base) to support the heavier column loads from the building
superstructure. Straight-shafted piles are formed by boring a hole
with an auger – a tool like a vast drill bit. The pile is cast
within this borehole by installing steel reinforcement and then
pouring concrete.
Construction of an underreamed pile is essentially the same, but
involves enlarging the base of the pile to increase its bearing
surface. Straight-shafted piles for Terminal 5 would be up to 2.1m
diameter, and underreams would be up to 6.2m diameter. Mott
MacDonald anticipated that underreams would be needed on 450 of the
main building’s 1,100 piles.
However, underreaming is time-consuming and carries higher safety
risks than construction of conventional straight-shafted piles, as
there is higher potential for collapse of the borehole sides. In
order to understand to what extent underreaming really was
necessary, our specialists devised unusual and rigorous tests to
determine how piles would behave. We designed the tests to reveal
the effects of swelling on the strength of the London clay and pile
shaft capacity over time.