
A series of pile tests provided a level of understanding that
informed foundation design for all of the T5 buildings. Four
straight shafted test piles were constructed by specialist
subcontractor Bachy Soletanche on the T5 site in 2002. In order to
determine the extent of skin friction and therefore pile shaft
capacity, we installed large polypropylene bags filled with water
into the pile bores at the base of the pile reinforcement before
concrete was poured.
The bags were connected to the surface by hoses, and by opening
valves on the hoses once concrete had cured it was possible to
isolate the pile bases completely from the bottom of the pile bores
– the water bags had created a 600mm deep void beneath each pile.
This enabled the piles to be jacked down in up to four 150mm
increments without the effects of end bearing influencing the test
results.
Mott MacDonald carried out testing of the piles at three month
intervals, enabling a clear picture to be built up of the piles’
initial capacity compared with their residual capacity – that is,
their strength before and after being moved. This simulated the
effect of the swelling ground moving relative to the piles. Testing
started with a single pile. After three months we moved the first
pile a second time and another pile for the first time. Another
three months on and we included a third pile in the tests. And we
tested the last pile for the first time at the end of a year.
Staggering the tests illustrated what changes were likely to occur
in the interaction between soil and structure over time.
We measured end bearing capacity on two further piles using the
innovative Osterberg Cell technique. Before concrete was poured we
had placed a steel plate and high capacity jack in the toe of each
pile. Our team activated jacks to push down against the bearing
plate and up against the pile. We gained an accurate value for end
bearing strength by measuring force exerted by the jack and
displacement of clay beneath the pile.