
Mott MacDonald carried out detailed option studies to determine the
most cost-effective structural solution for T5’s basement
structures. We determined that a composite steel system was to be
most economical in combination with the 9m by 18m grid of piled
foundations and also the most flexible, allowing for possible
changes to the building, including floor penetrations.
Floor beams consist of welded plate girders, all 1,200mm deep,
giving a consistent structural soffit level to simplify
co-ordination and installation of building services, which are
supported beneath. Different loading requirements are incorporated
by changing the girder plate thickness.
Construction of the floor forming the roof over the rail station
box comprises precast concrete inverted T beams with an in situ
cast reinforced concrete deck, spanning between steel girders. The
exposed soffit of the precast beams provide a high quality finish
over the station.
For T5B and T5C we adopted a regular foundation and column grid of
9m x 9m. Floors are of flat slab construction. Mott MacDonald
incorporated services openings early in the design. And for speed
of construction we used precast concrete T section beams to form
the roof over the tracked transit system tunnel and station in T5C.
Standardisation
The extensive areas of wall and slab construction enabled
significant standardisation of reinforcement and formwork. Most of
the reinforcement was prefabricated in the nearby Colnbrook
Logistics Centre, to which all construction materials were
delivered. Complete cages and mats of reinforcement for slab
construction were transported to site on a just-in-time basis. This
speeded up construction, enabled higher quality to be achieved as
well as improved safety.